The new 900 square foot interior data processing room and 5,000 square foot of exterior equipment platforms for data processing equipment. The Stadium is located in East Rutherford, NJ and the network was completed on September 2012. We are currently working on upgrading the system for additional capacity. FCArchitects provided the following services for the project:

  • Preparation of construction documents
  • Construction documents and specifications that met the clients network standard specifications and building code compliance
  • Exterior data processing equipment layout and supporting electrical service design
  • Interior data processing equipment layout – racks and support devices
  • DC plant and distribution
  • Grounding system design
  • Public utility coordination, electric service and fiber demark
  • Secondary electric service load calculations and electrical distribution
  • Heat gain and cooling calculations, cooling unit sizing and air distribution design
  • Associated coaxial cables and fiber components and wiring diagrams
  • DCA permitting process
  • Stadium owner retained FCArchitects to prepare construction documents for the Wi-Fi system, which was completed in 2012.

Thornton Tomasetti provided structural engineering consulting services.